Stockland’s 444 MW Sydney Data Center Plan Enters Public Review

Key PointsPublic exhibition of the EIS is a review step and not approval to build the Kemps Creek…
View more
- Public exhibition of the EIS is a review step and not approval to build the Kemps Creek campus.
- The EIS must show a Power Usage Effectiveness of 1.3 or better before the project can proceed.
- Stockland's roughly 450 MW secured platform figure is separate from Kemps Creek's campus capacity.
The NSW Planning Portal began public exhibition of the environmental impact statement (EIS) for Stockland Development’s proposed Aldington Road Data Centre on November 19, 2026. The two-building Kemps Creek campus has a stated maximum power consumption of 444 MW, with submissions accepted until December 17, 2026.
The State Significant Development remains under assessment, so exhibition is not authorization to build. Stockland’s October 19, 2026 operational update lists Kemps Creek as 50% Stockland-owned and targeted at AI/hyperscaler customers, giving the planning review direct relevance to its AI infrastructure strategy.
Power and Cooling Requirements
The amended Planning Secretary’s Environmental Assessment Requirements (SEARs), issued September 15, 2026, set out up to 360 MW of IT power consumption, data hall buildings as tall as 36.4 meters, ancillary offices, backup power and diesel storage, and a substation with distribution capacity of up to 1,000 megavolt-amperes. The IT figure is distinct from the portal’s campus-wide maximum, separating computing equipment from supporting infrastructure whose demand the EIS must also quantify.
On its project page, Stockland locates the proposal on industrial-zoned land in Western Sydney’s Mamre Road Precinct and says it is designed around air-cooling technology that does not rely on water for cooling. A March 2026 endorsement by the NSW Investment Delivery Authority recognized the project as private-sector investment in critical sectors including digital infrastructure.
Efficiency and energy supply form part of the approval test. The EIS must demonstrate the development’s ability to achieve a Power Usage Effectiveness score of 1.3 or less, equivalent to a five-star or better NABERS Data Centre Energy rating, and address state targets for Water Usage Effectiveness. It must also commit to matching operational electricity demand with NSW-based renewable energy supply at all times. These are assessment requirements, not measurements from an operating facility.
Backup-power and cooling systems must be modeled during unplanned outages, testing and maintenance. Noise and air-quality assessments must include cumulative effects from other proposed and approved data centers nearby, alongside separate work on traffic, water, biodiversity and utility infrastructure.
Stockland’s Development Platform
Stockland’s operational update describes its data center opportunity as a partnership with global operator EdgeConneX and reports approximately 450 MW of power secured across the platform, with four additional sites identified from its existing logistics pipeline. The secured-power figure is subject to final design, documentation and customer negotiations; it is platform-wide rather than a Kemps Creek capacity figure.
That distinction matters because the planning documents measure different things: secured power across Stockland’s portfolio, IT load at Kemps Creek, and the proposed campus’s maximum overall consumption. Keeping those measurements separate shows both the scale of the individual proposal and the earlier commercial and technical condition of the wider platform.
Other Sydney-Area Planning Records
The Wetherill Park Data Centre record is at the Prepare SEARs stage and describes a single four-storey building operating 24/7 with approximately 238 MW of total capacity and 170 MW of IT load. The works also include demolition and site establishment, an on-site substation and a transmission line. Stockland’s update identifies that site as 100% Stockland-owned and targeted at the same AI/hyperscaler customer category.
A separate portal record for 192 Narellan Road in Campbelltown is at the Prepare EIS stage. It describes construction and 24/7 operation of a 100 MW data center with a maximum building height of 30 meters. Both it and Wetherill Park remain earlier in the planning sequence than Kemps Creek’s exhibition.
For Stockland, Kemps Creek is the immediate test of whether a campus targeted at AI and hyperscaler customers can satisfy NSW’s efficiency, renewable-energy and cumulative-impact requirements. Public submissions and the remaining assessment steps precede any construction decision; the company anticipates a determination in 2027, an expectation rather than a fixed approval date.